AESL won a ₹4,700 crore Maharashtra TBCB transmission project to evacuate up to 4,500 MW of renewable and pumped-storage power, adding 562 ckm of lines and 9,000 MVA transformation capacity within 36 months. The win lifts its transmission order book to approximately ₹85,000 crore.